Wednesday, May 13, 2009

Results as of May 13, 2009

For this installment, I added a "long form" section. First for the short:

Totally successful: 2 out of 19
Mostly successful: 12 out of 19
Partially successful: 2 out of 19
Failure: 3 out of 19

The long form is where things get interesting. It turns out that while projects are coming out "successfully", it often is at unforeseen cost:

1. In terms of schedule, the project was finished (or canceled):

Early: 0 out of 8
On time: 2 out of 8
Late: 2 out of 8
Very late: 4 out of 8

2. In terms of budget, the project was finished (or canceled):

Under budget: 1 out of 8
On budget: 1 out of 8
Over budget: 5 out of 8
Way over budget: 1 out of 8

3. In terms of satisfaction, end users were:

Disappointed: 4 out of 8
Satisfied: 4 out of 8