Two more responses, new summary:
Totally successful: 3 out of 21
Mostly successful: 13 out of 21
Partially successful: 2 out of 21
Failure: 3 out of 21
The long form is where things get interesting. It turns out that while projects are coming out "successfully", it often is at unforeseen cost:
1. In terms of schedule, the project was finished (or canceled):
Early: 0 out of 9
On time: 3 out of 9
Late: 2 out of 9
Very late: 4 out of 9
2. In terms of budget, the project was finished (or canceled):
Under budget: 1 out of 9
On budget: 2 out of 9
Over budget: 5 out of 9
Way over budget: 1 out of 9
3. In terms of satisfaction, end users were:
Disappointed: 4 out of 9
Satisfied: 5 out of 9